
Glue Machine Systems in Corrugating Lines: Technical Guide
Complete guide to glue machines and adhesive application systems in corrugating lines, covering types, settings, maintenance, and optimization for board quality.
Technical Guides

Proper factory layout and installation planning can save months of time and significant cost when setting up a new corrugating line. This guide covers the essential requirements for a successful installation.
Phase 1: Site Selection and Building Requirements
Minimum clear height: 8-10 meters (for roll handling and maintenance access)
• 3-ply line (100-200 m/min): 60m × 15m minimum
• 5-ply line (150-250 m/min): 80m × 18m minimum
• High-speed line (250-350 m/min): 100m × 20m minimum
• Add 30-50% for paper storage, finished goods, and utilities
• Reinforced concrete, minimum 200mm thickness
• Load capacity: 5-10 tons/m² under machine sections
• Level tolerance: ±3mm over 10 meters
• Isolation joints between machine foundations and general floor
• Temperature: 15-35°C for consistent paper behavior
• Humidity: 50-65% RH (critical for paper and adhesive performance)
• Dust control: Adequate ventilation and filtration
• Lighting: 300-500 lux at operating level
Phase 2: Utility Requirements
• 3-ply line: 200-400 kW total connected load
• 5-ply line: 400-800 kW
• High-speed line: 600-1200 kW
• Voltage: 380V/415V three-phase (varies by region)
• Dedicated transformer recommended for lines above 300 kW
• Power factor correction to 0.9+
• Pressure: 6-8 bar (85-115 psi)
• Flow: 2-5 m³/min depending on line size
• Clean, dry air required (filtered and dried)
• Used for pneumatic controls, brakes, and splicers
• Steam boiler: 2-8 tons/hour capacity
• Steam pressure: 8-12 bar
• Condensate return system
• Water treatment for boiler feed
• Annual boiler inspection and certification required
• Electric heating only — no steam boiler needed
• Saves boiler investment ($50,000-200,000)
• Saves boiler room space (30-50 m²)
• No water treatment or emissions compliance for boiler
• Significantly simpler utility infrastructure
• Adhesive preparation: Clean water for glue kitchen
• Equipment cooling: Where applicable
• Fire suppression system
• Flow: 5-10 m³/hour typical
Phase 3: Factory Layout Design
1. Paper roll storage (near line entry, climate-controlled)
2. Mill roll stands (line entry point)
3. Single facer(s) and preheaters
4. Bridge conveyors
5. Glue machine and double backer
6. Slitter scorer and cut-off
7. Stacker and finished board storage
8. Waste handling and trim removal
• Glue kitchen: Adjacent to line, 20-40 m²
• Maintenance workshop: Near line, with overhead crane access
• Electrical room: Climate-controlled, accessible
• Quality lab: 15-25 m² for testing equipment
• Office and control room: Overlooking production floor
• Paper rolls in → Corrugating line → Finished sheets out
• Minimize transport distance for heavy paper rolls
• Finished board storage close to converting area
• Waste paper collection point accessible for recycling
Phase 4: Foundation and Anchoring
• Each major section requires independent foundation
• Foundation design provided by equipment manufacturer
• Typical depth: 800-1500mm below floor level
• Anchor bolts: Grade 8.8 or higher, epoxy-anchored
• Allow 28 days concrete curing before machine placement
1. Double backer (heaviest section, central reference point)
2. Single facer(s) — aligned to double backer
3. Bridge conveyors between sections
4. Mill roll stands at line entry
5. Slitter scorer, cut-off, and stacker at exit
6. Glue kitchen and piping connections
7. Electrical and control system wiring
8. Utility connections (power, air, steam/heat, water)
Phase 5: Installation Timeline
• Foundation construction: 4-6 weeks
• Equipment shipping: 4-8 weeks (depending on origin)
• Mechanical installation: 3-4 weeks
• Electrical and utility connection: 2-3 weeks
• Testing and commissioning: 2-3 weeks
• Operator training: 1-2 weeks
• Total project: 4-6 months from order to production
• No boiler procurement, installation, or certification
• No steam piping throughout the factory
• Simpler utility connections
• Faster commissioning (no boiler warm-up and tuning)
Phase 6: Pre-Installation Checklist
• All foundations completed and cured
• Building weatherproof and secure
• Electrical supply connected and tested
• Compressed air system operational
• Overhead crane or lifting equipment available
• Access roads for delivery trucks (container unloading)
• Storage area for crated equipment components
• Installation team mobilized (manufacturer technicians + local crew)
• Permits and inspections completed
Xuegong provides factory layout recommendations, foundation drawings, and on-site installation support for boiler-free corrugating line projects. Contact us for project planning assistance.
Related Articles